City of Edmonton Tower
The project broke ground March 3, 2015 and was constructed though to November 2016. The facility was opened to the public on Dec 5, 2016. This 28 story office building is the Ice District’s first new Tower to be constructed. Several more buildings to follow including Western Canada’s tallest tower…the Stantec Tower.
Design and Construction
General Contractor
- PCL
Our Subcontract Scope of Work
Supply and install:
- 3,365 manual shades
Approved Window Coverings
- SunProject Altex Commercial roll shades
- Model: MDL – 85 series
Job Safety Record
- C.O.R documentation maintained and recorded
- Zero Injuries
- No Near Misses
- Zero Lost Man Hours